Skip to main content
CPP
CRITICAL PATH PARTNERSForensic Schedule Analysis
DWG · CCDC 2 - 2020, Contract No. OCC-B2-2025 (Demo Data) / SHEET A-00
Claims Package · Cover Letter · Rev A
Extension of Time Claim

Claims Package Cover Letter Ontario Community College - B2 (Demo Data) · CCDC 2 - 2020, Contract No. OCC-B2-2025 (Demo Data)

Project
Ontario Community College - B2 (Demo Data)
Claimant
Northgate Constructors
Submitted To
Ontario Community College Owner Group
Date
2026-09-01
Total Time Claimed
9
Working days EOT requested
Delay Event
1
Exhibits
4
Response
30 DAYS
A-01

Claim Headline

summary of relief requested
Time Claimed
9 WD
total working days
Delay Events
1
analysed in Exhibit DE-01
Supporting Docs
5
documents indexed
Response Window
30 DAYS
written response requested
A-02

Correspondence Block

claimant · recipient · subject
From · Claimant
CompanyNorthgate Constructors
Address400 Example Road, Toronto, Ontario (Demo)
DateSeptember 01, 2026
To · Recipient
AttentionMs. R. Chen, Owner's Representative (Demo)
CompanyOntario Community College Owner Group
Address1 College Drive, Toronto, Ontario (Demo)
Subject · Reference
REEOT Claim: Ontario Community College - B2 (Demo Data)
ContractCCDC 2 - 2020, Contract No. OCC-B2-2025 (Demo Data)
BasisGC 6.5.1 (delay by the Owner or the Consultant)
A-03

Statement of Claim

opening narrative
Request for Relief

Northgate Constructors hereby submits a request for extension of time totalling 9 working days for the above-referenced project. Each delay event is documented in a separate exhibit referenced below.

The Contractor claims 9 working days pursuant to GC 6.5.1 (delay by the Owner or the Consultant) of the demonstration contract. Clause citations follow the demonstration contract and are stated for format; this is synthetic data.

Time Claimed
9 WD
Delay Events
1
Exhibits
4
Total Claimed
9WD
EOT REQUESTED
Critical-path impact: owner-directed change
A-04

Exhibit Index

register · all exhibits listed
A-04Exhibit Index: every exhibit in the package
4 exhibits — all listedExport CSV
ExhibitTitleFile
ACover Letter (this document)
DE-01Delay Event Analysis: Fire-spray application held for owner inspector availabilityOntario_Community_College___B2_Demo_Data_Exhibit_DE-01_Fire_spray_application_held_for_owner_inspector_availability.docx
WorkbookForensic Schedule Workbook
IndexSupporting Documents Index
A-05

Entitlement Summary

register · per-window working days
A-05Entitlement Summary: every claimed window listed
2 rows — all listed (incl. total)Export CSV
ExhibitWindowDescriptionWorking Days
DE-01Baseline → CurrentFire-spray application held for owner inspector availability9 WD
TOTAL CLAIMED9 WD
A-06

Contract Basis

entitlement clauses
Impacting Events
  • Fire-spray application held for owner inspector availability.
  • Total critical-path impact: 9 working days.
Response Required
  • Formal written response requested within 30 days per contract.
  • Contact the undersigned to schedule a discussion meeting.
A-06Contract Basis: event to clause map (all events listed)
1 event — all listedExport CSV
ExhibitEventContract Clause(s)
DE-01Fire-spray application held for owner inspector availabilityGC 6.5.1 (delay by the Owner or the Consultant)
A-07

Closing and Signature

request · undersigned
01Requested ActionResponse · 30 Days
We request a formal written response to this claim within 30 days in accordance with the contract. Please contact the undersigned with any questions or to schedule a meeting to discuss this submission. Respectfully submitted.
02UndersignedClaimant Signatory
Dana Fitkowski, Principal, Critical Path Partners, Northgate Constructors
A-08

Distribution and Provenance

CC list · package manifest
CC Distribution
Project file
Delay Event Analyses
1 analysis
Forensic Workbook
Schedule workbook included
Supporting Docs Index
5 documents
Contract Reference
CCDC 2 - 2020, Contract No. OCC-B2-2025 (Demo Data)
Submission Date
2026-09-01
Generated by CPP Claims Preparation · Project: Ontario Community College - B2 (Demo Data) · Claimant: Northgate Constructors · Engine cpm-engine v2.9.42Reproducible · standards-based