BasisGC 6.5.1 (delay by the Owner or the Consultant)
A-03
Statement of Claim
opening narrative
Request for Relief
Northgate Constructors hereby submits a request for extension of time totalling 9 working days for the above-referenced project. Each delay event is documented in a separate exhibit referenced below.
The Contractor claims 9 working days pursuant to GC 6.5.1 (delay by the Owner or the Consultant) of the demonstration contract. Clause citations follow the demonstration contract and are stated for format; this is synthetic data.
Fire-spray application held for owner inspector availability
9 WD
—
TOTAL CLAIMED
9 WD
A-06
Contract Basis
entitlement clauses
Entitlement Basis
The Contractor claims 9 working days pursuant to GC 6.5.1 (delay by the Owner or the Consultant) of the demonstration contract. Clause citations follow the demonstration contract and are stated for format; this is synthetic data.
Impacting Events
Fire-spray application held for owner inspector availability.
Total critical-path impact: 9 working days.
Response Required
Formal written response requested within 30 days per contract.
Contact the undersigned to schedule a discussion meeting.
A-06Contract Basis: event to clause map (all events listed)
Fire-spray application held for owner inspector availability
GC 6.5.1 (delay by the Owner or the Consultant)
A-07
Closing and Signature
request · undersigned
01Requested ActionResponse · 30 Days
We request a formal written response to this claim within 30 days in accordance with the contract. Please contact the undersigned with any questions or to schedule a meeting to discuss this submission. Respectfully submitted.
02UndersignedClaimant Signatory
Dana Fitkowski, Principal, Critical Path Partners, Northgate Constructors